DAY UNO ON NEWTOWN ROAD! ⚡️🚧

Another project underway for the Direct Drainage team! 💪

Today’s progress includes:

✅ Installation of a brand-new pumping station connecting into the new sewer system via a gravity-fed manhole.

✅ Scaffolding access ramp installed to ensure safe access throughout the works.

✅ 63mm overpumping pipework installed, insulated and protected with sand and warning tape in accordance with regulations.

QUALITY IS KEY IN EVERYTHING WE DO! 💯

We don’t believe in rushing jobs or cutting corners. We believe in doing things properly, safely and professionally the first time.

Get in, get the job done right and leave a quality finish! 👊