An Industrial Abandoned Fuel Station Removal, Hazardous Soils Removal with Engineered Compaction Testing, Grading and Paving for a Private Client for A Parking Lot Expansion for Large Trucks.

Start to Finish this project took 4 days: 1 day for demolition and cleanup, 1 Day for Hazardous Removal, remediation and Haul off, 1 Day for Backfill Grading and Compaction and 1 day to Pave, Seed and Straw